COCOMO Model – Development Time Calculation

The COCOMO (Constructive Cost Model) is a software estimation model used to calculate development effort, time, and cost based on project size (measured in KLOC – Thousand Lines of Code).

 1. Types of COCOMO Models

COCOMO has three models based on project complexity:

Basic COCOMO Model → Quick estimation (less accuracy)
Intermediate COCOMO Model → Includes cost drivers
Detailed COCOMO Model → Most accurate with multiple factors

We will focus on the Basic COCOMO Model here!

2. Basic COCOMO Model Formula

The effort (E) in person-months (PM) and development time (T in months) is calculated as:

Effort Equation:

E=a×(KLOC)bE = a \times (KLOC)^b

Development Time Equation:

T=c×(E)dT = c \times (E)^d

where a, b, c, d are constants that depend on the project type.

3. COCOMO Model Categories & Constants

Project Type a b c d Example Projects
Organic 2.4 1.05 2.5 0.38 Small teams, well-understood projects
Semi-Detached 3.0 1.12 2.5 0.35 Medium-sized projects, mixed experience
Embedded 3.6 1.20 2.5 0.32 Large, complex systems

 4. Example Calculation (Basic COCOMO Model)

Example:

A software project is estimated to have 50 KLOC (50,000 lines of code) and is categorized as a Semi-Detached project. Calculate the Effort (E) and Development Time (T).

Solution:

From the table, for Semi-Detached Projects:

  • a=3.0a = 3.0, b=1.12b = 1.12
  • c=2.5c = 2.5, d=0.35d = 0.35

Step 1: Calculate Effort (E)

E=3.0×(50)1.12E = 3.0 \times (50)^{1.12} E=3.0×64.36E = 3.0 \times 64.36 E=193.08 Person-MonthsE = 193.08 \text{ Person-Months}

Step 2: Calculate Development Time (T)

T=2.5×(193.08)0.35T = 2.5 \times (193.08)^{0.35} T=2.5×7.24T = 2.5 \times 7.24 T=18.1 MonthsT = 18.1 \text{ Months}

Final Answer:

  • Effort = 193.08 Person-Months
  • Development Time = 18.1 Months

 5. Key Takeaways

Basic COCOMO Model is a simple way to estimate effort and time.
Larger projects require more time, effort, and resources due to complexity.
More advanced versions (Intermediate, Detailed COCOMO) consider multiple cost drivers for better accuracy.

 Do you want more examples or explanations on COCOMO variations? Let me know!

Development Time Calculation in cocomo model: basic cocomo model cocomo model example

COCOMO Models



Diznr International

Diznr International is known for International Business and Technology Magazine.

Leave a Reply

Your email address will not be published. Required fields are marked *

error: